International Development Grant

Route des rails - Road Infrastructure Project I

Project Number: CA-3-A034109001

Status: Closed

Country/Region:

Haiti 100.00%

Maximum Contribution: $15,485,023.00

Start Date: March 19, 2008

End Date: August 30, 2013

Duration: 5.4 years

Project Description

This project aims to reduce traffic on the national highway that runs through the commune of Carrefour by improving the flow of traffic in and out of Port-au-Prince. It also aims to improve the local economy and safety for the citizens of Carrefour. The project's main components are: construction of one kilometre of road installation of equipment and facilities over 6.8 km of road (lighting drainage traffic signals and landscaping) construction of a bus terminal and related studies. This project is one of two parts of a $15.5 million contribution. It has been divided for administrative reasons.

Progress & Results Achieved

Results achieved by this project which ended in March 2013 include: Construction of the Route des Rails is fully complete. Set-up and installation of facilities such as lighting drainage signage and landscaping along 6.8 kilometres of the road is complete. Construction of the road improves traffic in this sector considerably facilitates access to the city of Port-au-Prince from the south and reduces traffic congestion in a commune of 469 019 inhabitants. These results have contributed to reducing the transit time between the South and the capital which reduces traffic congestion and transport costs for goods destined for the market. More than four million people benefit from this road.

Key Information

Executing Agency:
IDB - Inter-American Development Bank

Reporting Organization:
Global Affairs Canada

Program:
NGM Americas

Last Modified:
September 19, 2025

Development Classifications

DAC Sector:

Road transport 70%
Urban development and management 30%

Aid Type: Contributions to specific-purpose programmes and funds managed by implementing partners

Collaboration: Bilateral

Finance Type: Aid grant excluding debt reorganisation

Selection Mechanism:
Pre-APP

Policy Markers
Level 1 Urban issues
Major Funding (>$1M)
Budget Breakdown
2007-04-01 to 2008-03-31 $15,485,023 CAD
Geographic Information
000
Project Number: CA-3-A034109001